| 建筑师会准备以下文件: |
 |
|
|
 |
| 地盘规划图(Site Plan / Layout Plan) |
|
|
 |
| 排水图(Drainage Plan)- C&S Engineer 负责 |
|
|
 |
|
|
 |
| 排污系统图(Sewerage Plan)- 需提交 IWK / SPAN |
|
|
 |
|
|
 |
|
|
 |
|
|
|
 |
| 这一步你只需提供: |
 |
| Industrial Title(新地契) |
 |
业主公司资料
(SSM / Form 24 & 49 / Section 58 & 78) |
|
|
| |
| |
|
|
 |
| 所有工厂开发都必须先获得:KM – Planning Approval(规划批准) |
| |
| 需要提提案包括: |
 |
Land Use Confirmation
(你已工业地 – 更容易通过) |
|
|
 |
|
|
 |
|
|
 |
| Building setbacks (前后左右退距) |
|
|
 |
|
|
 |
| Heavy vehicle circulation plan |
|
|
|
 |
| 批准时间:1-3 个月 |
|
| |
|
|
| |
|
|
 |
| KM 批准后,建筑师会向 MPKU 提交 建筑图(Building Plan Submission)。这一步会涉及多部门技术审核,需获得技术部门的“支持(clearance)”: |
| Fire & Rescue Department (消防局) – 必须 |
|
|
 |
| Tenaga Nasional Berhad (TNB) – 电力 |
|
|
 |
| Syarikat Air Johor (SAJ) – 水供 |
|
|
 |
|
|
 |
| Department of Irrigation & Drainage (JPS) – 排水渠 |
|
|
 |
| Public Works Department (JKR) – 道路入口 (如工厂入口接主干道) |
|
|
|
 |
| Department of Environment (DOE) – 如果工厂有排污/噪音/危险物质 |
|
|
 |
| 审核时间:2–6 个月(依工厂规模) |
|
| |
| |
|
|
 |
| 一旦 MPKU 批准建筑图,你就能:正式开工(Start Construction) |
| |
| 需要: |
 |
| Notice of Commencement(开工通知) |
|
|
 |
|
|
 |
|
|
|
|
| |
| |
|
|
 |
| 施工期间须由: |
 |
Architect
(SP – Submitting Person) |
 |
| Professional Engineers (PE) |
|
 |
| 进行监督、填写工地日志、定期到场检查。 |
| |
| 重要事项: |
 |
| 遵守 Bomba 要求(hydrant、hose reel、smoke detector 等) |
|
|
 |
|
|
 |
|
|
|
|
| |
| |
|
|
 |
| 工业建筑完工后,由 Architect 签发 CCC 取代旧时代的 CFO。 |
| |
| CCC 必须符合所有: |
 |
|
|
 |
| TNB electricity meter installation |
|
|
 |
| SAJ water meter installation |
|
|
 |
| Sewerage connection approval |
|
|
 |
| Structural completion certification |
|
|
 |
|
|
|
 |
| CCC = 建筑正式合法,可投入使用或出租。 |
|