| Upon KM approval, the Architect will submit the Building Plan to MPKU for technical clearance. Clearances required from: |
| Fire & Rescue Department (Bomba) – Mandatory |
|
|
|
| Tenaga Nasional Berhad (TNB) – Electricity |
|
|
|
| Syarikat Air Johor (SAJ) – Water supply |
|
|
| |
| IWK / SPAN – Sewerage system |
|
|
|
| Department of Irrigation & Drainage (JPS) – Drainage |
|
|
|
| Public Works Department (JKR) – Road access to main roads (if applicable) |
|
|
|
| |
| Department of Environment (DOE) – If wastewater, noise or hazardous materials are involved |
|
|
 |
| Note: Processing time: approximately 2–6 months, depending on project scale. |
|
| |
| |
|
|
 |
| Once the Building Plan is approved, you may proceed to: Commence construction works |
| |
| Requirements prior to construction: |
 |
|
|
|
| Proof of CIDB Levy payment |
|
|
|
| Main contractor’s valid CIDB registration |
|
|
|
|
| |
| |
|
|
 |
| During construction, the project must be supervised by: |
|
Architect
(SP – Submitting Person) |
|
Professional Engineers (PE) |
|
| |
| Key compliance matters: |
 |
| Full compliance with Bomba fire safety requirements |
|
|
|
| Compliance with approved drainage and sewerage design |
|
|
|
| Compliance with environmental approvals (if applicable) |
|
|
|
|
| |
| |
|
|
 |
| Upon completion of the industrial building, the Architect will issue the CCC, which replaces the former CFO system. |
| |
| The CCC is only issued after confirmation of: |
 |
|
|
|
| TNB electricity meter installation |
|
|
|
| SAJ water meter installation |
|
|
| |
| Sewerage connection approval |
|
|
|
| Structural completion certification |
|
|
|
| Endorsements from all consultants |
|
|
|
 |
| Note: The CCC certifies that the factory is legally completed and may be occupied or leased. |
|